Project Description

In March of 2024, UBIT started replacing 1,200 edge switches and 100 pairs of building aggregation switches, along with migrating the intra-switch connections from copper cabling to fiber optic.  These network switches are responsible for providing more than 45,000 wired Ethernet connections, within more than 125 buildings, spread across UB's three campuses and other off-campus locations. 

These connections provide service to faculty, staff, and student computers, Wi-Fi access points, VoIP telephones, printers, cameras, sensors, vending machines, classroom equipment, and much more.  

Project Fast Facts

Start:
March 2024

Project Manager:
Joseph Pautler, Network Architect

Total Network Switches:
1,400

Total Buildings and Complexes:
125

Total Telecommunications Rooms:
625

Total Ethernet Connections:
45,000

Advantages

Prior to the procurement and deployment, UBIT conducted a thorough evaluation of products and pricing from the leading manufacturers, in order to identify the best solution for UB.  The new switches and fiber optic connectivity provide the university with many benefits, including higher bandwidth between switches (50Gbps), higher bandwidth available to each device (up to 10Gbps), more Power-over-Ethernet (PoE) available to each device (up to 90W), capability for higher bandwidth to each building in the future (up to 200Gbps), and long-term hardware & software support from the manufacturer.

Project Schedule

Building Campus Tentative Start Finish
Computing Center (test building) North 3/25 4/12
Jacobs & Alfiero Center (pilot building) North 4/15 5/17
Cooke / Hochstetter / Dorsheimer North 5/13  
Natural Sciences Complex North 6/10  
Mathematics Building North 7/1  
Fronczak Hall North 7/8  
Baldy Hall North    
O'Brian Hall North    
Park Hall North    
Lockwood Memorial Library North    
Student Union North    
Clemens Hall North    
Center for the Arts North    
Davis Hall North    
Furnas Hall North    
Ketter Hall North    
Jarvis Hall North    
Bonner Hall North    
Bell Hall North    
Knox Lecture Hall North    
Norton Hall North    
Talbert Hall North    
Capen Hall North    
Baird Hall North    
Slee Hall North    
Squire Hall South    
Kimball Tower South    
Cary Hall South    
Farber Hall South    
Farber Hall Annex South    
Sherman Hall South    
Sherman Hall Annex South    
Biomedical Research Building (BRB) South    
Biomedical Education Building (BEB) South    
Pharmacy Building South    
Acheson Hall Annex South    
Parker Hall South    
Abbott Hall South    
Wende Hall South    
Diefendorf Hall South    
Crosby Hall South    
Hayes Hall South    
Hayes Hall Annex A South    
Building Campus Tentative Start Finish
Hayes Hall Annex C South    
Michael Hall South    
South Campus Childcare Center A South    
Allen Hall South    
Harriman Hall South    
Beck Hall South    
Townsend Hall South    
220 Winspear Service Building South    
250 Winspear Service Center South    
Mackay Heating Plant South    
Howe Research Building South    
South Campus Electric Substation Building South    
South Campus Pump House South    
Clark Hall South    
COE Bioinformatics Life Sciences Downtown    
Clinical Translational Research Center Downtown    
Research Institute On Addictions Downtown    
UB Downtown Gateway Downtown    
Eve Educational Opportunity Center Downtown    
1176 Main Street (Ross Eye Institute) Downtown    
955 Main Street (JSMBS) Downtown    
Alumni Arena North    
UB Stadium North    
Murchie Family Fieldhouse North    
UB Commons North    
Crofts Hall North    
Beane Service Center North    
Helm Facility Warehouse North    
Statler Commissary North    
Sustainability Center North    
Center For Tomorrow North    
Baker Chilled Water Plant North    
North Campus Chemical Storage Building North    
North Campus Electric Substation Building North    
Bissell Hall North    
Campus Mail Center North    
North Campus Childcare Center North    
Baird Research Park Off    
4350 Maple Rd (UB Student Health Services) Off    
Libraries Annex Off    
Anderson Art Gallery Off    
President's House Off    
Residence Buildings
Building Campus Tentative Start Finish
Hadley Village North    
South Lake Village North    
Flint Village North    
Creekside Village North    
Greiner Hall North - Ellicott    
Red Jacket Quadrangle North - Ellicott    
Evans Quadrangle North - Ellicott    
Richmond Quadrangle North - Ellicott    
Wilkeson Quadrangle North - Ellicott    
Spaulding Quadrangle North - Ellicott    
Academic Center North - Ellicott    
Fargo Quadrangle North - Ellicott    
Roosevelt Hall North - Governors    
Clinton Hall North - Governors    
Dewey Hall North - Governors    
Lehman Hall North - Governors    
Flickinger Court Off    
Goodyear Hall South    
Clement Hall South    
UBMD Practice Plans
Building Campus Tentative Start Finish
5959 Big Tree Road Off    
1010 Main Street Off    
1020 Youngs Road Off    
235 Windward Road Off    
4225 Genesee Street Off    
3580 Sheridan Drive Off    
1000 Youngs Road Off    
1237 Delaware Avenue Off    
1404 Sweet Home Road Off    
179 Bryant Street Off    
2465 Sheridan Drive Off    
4180 Abbott Road Off    
4498 Main Street Off    
4955 North Bailey Avenue Off    
5102 Transit Road Off    
5851 Main Street Off    
6934 Williams Road Off    
850 Hopkins Road Off    
Erie County Medical Center (ECMC) Off    
111 North Maplemere Road Off    
620 10th Street Off    

Common Questions