Click is being rolled out by module starting with the IRB.
9/15/2015 | IRB Staff only Training |
9/21/2015 - 12/23/2015 | CLICK IRB Software Training |
10/16/2015 | IRBNET no long accepting new submissions |
11/1/2015 | Go Live for IRB CLICK Module |
1/1/2016 - 2/29/2016 | UAT Testing |
3/1/2016 - 6/30/2016 | Soft Roll Out |
5/1/2016 - 6/30/2016 | Training and voluntary use by researchers |
7/1/2016 | Go - Live for all agreements |
1/28/2016 - 1/29/2016 | EH&S Staff only Training |
2/8/2016 - 3/31/2016 | Click IRB Software Training |
2/15/2016 | Click Safety Pilot |
3/1/2016 | Click Safety Go Live fore rest of UB |
Implementation Phase is between 10/1/2015 and 6/30/2016. The tentative go live date for this module is October 2016.
Implementation Phase is between 10/1/2015 and 12/31/2015. The tentative go live date for this module is July 2016.
Implementation Phase is between 1/1/2016 and 3/31/2016. The tentative go live date for this module is Summer 2016.
UB students and non-UB staff who need access to the Click Portal can register for an account here.